There may be more than one critical path in a project network.
b. if one of the activities on the critical path isβ delayed, the entire project will be delayed.
c. the critical path is the sequence of activities between aβ project's start and finish that takes the shortest time to complete.
d. the activities along the critical path determine the completion time of the project.