A firm starts work with 110 employees for the 1st week. The number of employees rises by 6% per week. How many weeks will it take for 250 persons to be employed?
110 x 1.06 = 116.6 Now if 116.6 is x repeat this step till you get 250 people X x 1.06 , so it will take roughly 14-15 times to get 250 employees but 14 times is the closer one