Answer:
$6,788
Explanation:
The computation of the supplies cost in the planning budget is shown below:
= Supplies cost per month + number of frames in planned activity × per frame cost
= $1,640 + 572 frames × $9
= $1,640 + $5,148
= $6,788
We simply added the supplies cost and the planned frame cost so that the supplies cost for the planning budget could come