In December 2014, Shire Computer’s management establishes the 2015 predetermined overhead rate based on direct labor cost. The information used in setting this rate includes estimates that the company will incur $747,500 of overhead costs and $575,000 of direct labor cost in year 2015. During March 2015, Shire began and completed Job No. 13-56. 1. What is the predetermined overhead rate for year 2015?

Respuesta :

Answer:

Estimated manufacturing overhead rate= $1.3 per direct labor dollar.

Explanation:

Giving the following information:

Estimated overhead cost= $747,500

Estimated direct labor cost= $575,000

To calculate the estimated manufacturing overhead rate we need to use the following formula:

Estimated manufacturing overhead rate= total estimated overhead costs for the period/ total amount of allocation base

Estimated manufacturing overhead rate= 747,500/575,000= $1.3 per direct labor dollar.