Answer:
correct option is b. $ 30
Explanation:
given data
overhead cost = $15,000
direct labor hours = 5,000
required direct labors hours = 10
solution
we get here Fixed Overhead Rate that is
Fixed Overhead Rate = estimated overhead cost ÷ direct labor hours ........1
Fixed Overhead Rate = [tex]\frac{15000}{5000}[/tex]
Fixed Overhead Rate = $3 per labor hour
and
Job overhead applied express as
overhead = Fixed Overhead Rate × required direct labors hours ..........2
overhead = $3 × 10
overhead = $30
so correct option is b. $ 30