The Jase Company allocates overhead based on a predetermined overhead rate of $9.00 per direct labor hour. Job J904 required 8 tons of direct material at a cost of $600 per ton and took employees who earn $21 per hour a total of 80 hours to complete. What is the total cost of Job J904?

Respuesta :

Answer:

The total cost of job J904 = $7,200

Explanation:

Direct material cost= 8 tons * $600/ ton    =  $4,800

Direct labour cost  =  80 hours * $21/ hour = $1,680

Overhead cost       =  80 hours * $9/ hour  =  $720

Total                                                              = $7,200