contestada

Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported:



Inspection time 0.6 days
Wait time (from order to start of production) 15.8 days
Process time 2.8 days
Move time 1.3 days
Queue time 3.9 days


Required:
1.
Compute the throughput time. (Round your answer to 1 decimal place.)



2.
Compute the manufacturing cycle efficiency (MCE) for the quarter. (Round your answer to the nearest whole percentage (i.e., 0.12 should be entered as 12).)