Answer: Option D
Explanation: Internal rate of return ,denoted as IRR, is the rate at which the net present value of a capital investment is zero. It is the rate at which the cash flows of the investment are discounted back to calculate the present value.
While, required rate of return is that return which an investor expects to achieve over time from a capital project.
Thus, one would only select a capital project only if the NPV of a project is positive which can only happen when the return on investment, that is, IRR, is greater than cost of capital, that is, required rate of return.