A small project consisting of eight activities has the following characteristics: Time-Estimates (in wecks) (i) Draw the PERT network for the project. (ii) Prepare the activity schedule for the project. (iii) Determine the critical path. (iv) If a 30 - week deadline is imposed, what is the probability that the project will be finished within the time limit?