The latest finish time for a specific activity must be the same as or earlier than the earliest of all the latest start times of all the activities emerging directly from that specific activity. Which of the following statements accurately describes this condition?
a. The latest finish time for a specific activity must be earlier than the earliest of all the latest start times of all the activities emerging directly from that specific activity.
b. The latest finish time for a specific activity must be the same as the earliest of all the latest start times of all the activities emerging directly from that specific activity.
c. The latest finish time for a specific activity must be later than the earliest of all the latest start times of all the activities emerging directly from that specific activity.
d. The latest finish time for a specific activity must be equal to the earliest of all the latest start times of all the activities emerging directly from that specific activity.